Aceh residents raise S$72,000 to rebuild key bridge after months of waiting
Residents in Indonesia's Aceh Province raised more than S$72,000 to repair a critical bridge and road connection after months of waiting for government reconstruction following devastating floods and landslides.

- Residents raised more than S$72,000 to repair the Enang-Enang Bridge and adjoining road.
- The bridge reopened on 2 July 2026 after nearly eight months of disruption.
- The government says permanent reconstruction will continue to meet safety standards.
Residents in Indonesia’s Aceh Province have raised more than S$72,000 (Rp1 billion) to repair a key bridge and road connection after spending months waiting for government action following a disaster that cut off access to their communities.
The community-funded reconstruction of the Enang-Enang Bridge in Pintu Rime Gayo District, Bener Meriah Regency, has drawn national attention and renewed scrutiny of the pace of post-disaster infrastructure recovery in the province.
The bridge and adjoining road were severely damaged by floods and landslides that struck Aceh in November 2025. The route serves as a vital gateway to the Gayo Highlands, connecting residents to schools, healthcare facilities, markets and agricultural distribution networks.
For nearly eight months after the disaster, residents were forced to rely on longer alternative routes, increasing travel times and disrupting daily activities, including the transport of agricultural produce.
Frustrated by the prolonged lack of repairs, local residents began collecting donations to restore the damaged infrastructure themselves.
On 2 July 2026, community representatives announced that the repaired road and bridge had been reopened to traffic.
“Today we officially reopen the road. The asphalting works and bridge repairs have been completed. Thank you to everyone who contributed,” said Sahrial Abadi, who coordinated the community initiative.
The reopening attracted large crowds from surrounding areas, with residents gathering to witness vehicles once again crossing the route after months of disruption.
According to organisers, donations collected from residents exceeded S$72,000 (Rp1 billion). The funds were raised independently and did not come from the national government budget, the Aceh provincial budget or the Bener Meriah regency budget.
Sahrial said approximately S$37,800 (Rp526 million) had been spent on the road and bridge repairs, while the remaining around S$39,900 (Rp555 million) would be used for additional works, including retaining walls, places of worship and other public facilities.
The initiative emerged amid growing frustration over the slow pace of reconstruction following the disaster.
The viral attention surrounding the community-funded project coincided with announcements from Indonesia’s Ministry of Public Works that it was accelerating permanent repairs to several bridges and national road sections damaged by disasters across the province.
Public Works Minister Dody Hanggodo said the government remained committed to maintaining the functionality and connectivity of national roads in Aceh.
“Repairs are being carried out to ensure that bridges are once again safe to use, so that community connectivity and logistics distribution can be maintained,” Dody said on 7 July.
The ministry said permanent rehabilitation works are under way on several major infrastructure projects across Aceh.
In Southeast Aceh Regency, reconstruction of Lawe Mengkudu I Bridge, which connects the area with Gayo Lues Regency, had reached 83.72 per cent completion by early July 2026. The original bridge was demolished after being damaged by a disaster and is being replaced with a new structure.
In Central Aceh Regency, permanent construction of Lumut Bridge had reached 73.80 per cent completion. Works are currently focused on stone masonry along the bridge approaches to strengthen the structure and protect the roadway.
Meanwhile, rehabilitation of Ulee Langa Bridge in North Aceh Regency had reached 72.79 per cent completion as of 1 July 2026. Remaining works include concrete curing and the fabrication of steel deck components.
The ministry is also carrying out permanent repairs on a number of national road sections throughout Aceh.
Along the province’s eastern corridor, work is being conducted on 13 national road segments, including sections connecting Beureunuen and the Pidie Jaya border, Meureudu and Bireuen, Peureulak and Langsa, and Kuala Simpang and the North Sumatra border.
Along the western corridor, repairs are focused on the Genting Gerbang–Celala–Central Aceh/Nagan Raya border route and the Central Aceh/Nagan Raya border–Lhokseumot–Jeuram route.
In the Central Aceh corridor, authorities said 13 bridges and 322 landslide locations had been restored to functional condition. Ten of those bridges are scheduled for permanent reconstruction during 2026.
The projects cover several regencies, including Central Aceh, Gayo Lues, Southeast Aceh and Bener Meriah. In addition to road and bridge repairs, works include slope stabilisation and riverbank reinforcement aimed at reducing future infrastructure damage.
Following public attention on the Enang-Enang Bridge project, Public Works Ministry Secretary-General Apri Artoto said the government would continue with its own bridge construction programme in Bener Meriah despite the community-led repairs.
He said the ministry had concerns about structural safety if the bridge was built solely through community initiatives.
“What is certain is that our construction programme at the Ministry of Public Works will continue. Given concerns over public safety, if the bridge is built entirely through community self-help efforts, we are concerned about the safety of the structure. Therefore, we will proceed with our programme,” Apri said.
The Enang-Enang Bridge was severed when floods and landslides struck Aceh in November 2025. The crossing serves as a critical transport link for residents, enabling the movement of agricultural products and providing access to schools and healthcare facilities.
During the months-long disruption, residents were forced to use longer alternative routes while awaiting repairs.
The government has stated that official construction works will still be carried out to ensure the bridge meets safety standards and provides reliable long-term infrastructure for local communities.
The ministry also urged residents to prioritise safety during both construction activities and future use of the bridge.
The Enang-Enang project has become a prominent example of a community financing and carrying out repairs to essential infrastructure after months of waiting for government-led reconstruction following a natural disaster.








